22.5 MWp Ground-Mounted Solar Project with K2 Pi-Rack

Gutengermendorf, Germany

Installation Insights

Installation speed 20-30% above the original project plan

Module installation with K2 Pi-Rack is highly time-efficient thanks to the double-sided insertion profiles and screw-free module fastening.

As a result, installation progress to date is running 20-30% ahead of the original schedule, putting the overall construction progress significantly ahead of plan.

Suitable Foundations Even for Challenging Ground Conditions

All steel components of the K2 Pi-Rack system, including the driven piles, are protected by a zinc-magnesium-aluminium coating.

Due to the site’s ground conditions, including a peat layer, two different pile embedment depths are being used in this project.

Share

Lebanon

St. John Hospital in Lebanon

More
Zlatibor, Serbia

World’s longest gondola lift with K2 Dome 6 Classic LS

More
Bad Mergentheim, Germany

Bespoke solution at German school

More

SUBSCRIBE TO OUR NEWSLETTER

Stay updated: New features, updates & more

Subscribe now!
Need help?