Technical implementation:
Immediately after locating the purlins and determining the cable routing, the K2 MiniRails and SolarEdge Optimisers were installed on the roof. The solar modules were then mounted and fixed with K2 clamps, and the earthing and cable duct were laid up to the DC and AC distribution box. The inverter was finally installed and the team pulled the feed-in cable 35 metres to the WLAN-enabled Linky meter, which communicates directly with the internet as a so-called SmartMeter. To validate the installation specifically in France, an organisation was commissioned to verify electrical compliance. Thus, the installation could be successfully put into operation directly.